Well those pesky soil reports did come back and suggest that
we required piering – making us a 650sq block. 1.2-2.4m fall left to right, H
class waffle slab. The cost went up to a further $15K over our very detailed
estimate from another reputable builder creating issues for us with affording our upgrades. We have spent some time fluctuating
between happy and unhappy campers. Right now we are in the down camp again
having received an estimate site start of late November. We had originally been
very clear on needing an October site start and it does feel like after some
significant fluffing around and about 11 emails since August asking for things
to be processed promptly, here we are.
We do feel though that PD attempt to resolve any concerns
that we raise when we raise them which is a large part of what directed us to
them as a builder in the first place. However it is draining having to chase up
on so many levels. Hope that having the house plan we love in the end will make
up for all the palaver.
Our extremely competent BC [S] has resigned – is it just me
or do they have some crazy big turnover in there? Unfortunately not filling me
with confidence. Hope to be back blogging again soon with a site start date. In
the meantime, we finally got a little sold sticker on our land board ;P.
OH! We also found out the house number we will be on our street - funny how the little things feel like very exciting news :)