Timeline

Deposit 21/08/2011
Tile Appointment 06/10/2011
Colour Appointment 04/10/2011
Contract Appointment 11/10/2011
Site Start/Cut 24/11/2011
Slab Poured 9/12/2011
Frame 19/12/2011
Lock Up Comp
Fixing?
PCI?

Handover?